As part of the work to get CRH ready for the construction of our new hospital building, directional drilling will start today, Monday, 20th April on the grassy area next to the wall in the Women and Children's car park. The drilling will take about five weeks and is part of getting the groundwork ready for laying new pipework.  

Due to this work, from Thursday, 30th April 19 car parking spaces will be out of use in the W&C car park for around seven days. We appreciate our colleagues and patients using other ways to get to CRH, including public transport, while patient and visitor parking is limited. 

Pedestrian routes will still be open.

Other work on site continues, including removing the glass panels above the Women and Children's entrance.