CHS and their contractors will be carrying out essential electrical maintenance work on the electrical switch gear at HRI this coming Thursday, 30th October, between 05:30 and 06:00.
The affected areas (listed below) will experience a momentary interruption of all power for approximately 15 seconds (Theatres will have battery back-up) until the generator kicks in. Once the site returns to mains power there will be no disruption.
Please remember to switch off computers correctly when leaving work prior to the electrical shutdown. This means computers must be switched off at the socket. If this does not happen there is a risk that data on display will be lost.
Prior to any electrical work starting, CHS will visit critical areas such as ED, Theatres and Pathology to ensure colleagues are aware of the planned work and to ensure it is safe and appropriate to it out.
All lifts will be appropriately signed and checked during the power interruptions.
Please direct all queries on the day HRI Switchboard on 01484 342000.
Any queries around this work prior to the day should be directed to the Service Performance Team on Extension 2439 or 2530. Or email: mandy.carr@cht.nhs.uk or call Joe Wright (CHS) on 07386 699346 / 07791 525151.
Details of the areas affected by this work are show below. Please check the lists carefully for the work happening between 05:30 and 06:00:
- Estates Yard Generator 26/10/24
- Block 2 including lifts A2, B2, C2 and J2
- IT Server Room
- Boiler House
- Main Kitchen
- Laundry
- OPD (Path labs, Mortuary, Lifts L,M, N and P)
- New ED
- Theatres 2 4 6