Just seven weeks ago we started piling work on our new Multi-Storey Car Park (MSCP) at CRH, and in that short time 289 individual concrete pillars have been put into the ground and filled. The pillars will provide the stability to the car park.
Finishing the piling work means that we are making good progress on the construction of the MSCP. In the coming weeks the pillars will be capped with more concrete before pre-cast concrete panels and steel sections of the building are bought on to site.
On Friday last week, new hoardings also went up around the car park. The hoardings show people what the car park will look like once finished, and where to find more information about the Foundations for our Future programme.