Unfortunately, the essential electrical work planned for this coming weekend at CRH will no longer go ahead. This is due to a delay with our external contractors who were carrying out the work. Thank you to all teams and services for the time and effort in planning for the work, and we will keep you updated on a further date.
Essential electrical work will be taking place at CRH on Saturday, 14th June (08:00 – 14:00 approx) and Sunday, 15th June (06:00 – 09:00 approx). This work is to plug the new electrical substation which will be needed for construction of the new Multi-Storey Car Park.
Affected services will experience a momentary interruption of power for no more than 10 seconds at the start of the work.
Throughout the work:
- White sockets / switches will not work (non-essential power)
- Red sockets / switches will work through generators.
- Loss of power < 10 seconds at either side of the switch on / off
- Emergency lighting will remain
- Equipment which has a UPS will work as normal throughout – no interruption
The details of which teams affected on each day are listed below.
Saturday, 14th June (08:00 – 14:00 approx):
- Block N (ISS, Medical Engineering, Offices)
- Block L (Neurophysiology and Accommodation)
- Diabetes Centre and OH
- Block G (Draeger Building / Histology)
- Autoclaves 1&2
- Medical Records
- Bbraun Room
- Pharmacy Bulk Store
- THIS server room
- Trust Offices and Post Room
Sunday, 15th June (06:00 – 09:00 approx)
- Block H – Mortuary,. Pathology, Office Accommodation
- Renal
- Catering lower ground including meal assembly and wash up
If you have any questions:
- Prior to the work please contact Val Rigg (val.rigg@cht.nhs.uk) or Sophie Box (sophie.box@cht.nhs.uk)
- During the works, please contact help desk on ext. 4600
The electrical work supports the Foundations for our Future programme, which is our long-term vision to transform our services in Calderdale and Huddersfield. Further information about the programme can be found online: https://future.cht.nhs.uk/home